Lab 850 Commissioning
15
ba75553e03 01/2006
3 Commissioning
3.1 Scope of delivery
! Lab 850 laboratory meter
! Power pack
! 4 batteries 1.5 V Mignon type AA
! Transparent cover
! Stand with stand base (S4D)
! Operating manual
! CD-ROM
3.2 Initial commissioning
Perform the following activities:
! Switch on the meter
! Set the date and time
! Connect the power pack (for line power operation only).
Switching on the meter
Setting the date and
time
Connecting the power
pack
Caution
The line voltage at the operating site must lie within the input
voltage range of the original power pack (see page 47).
Caution
Use original power packs only (see page 47).
1 Switch on the meter with <On/Off>.
A display test is briefly displayed.
2 See page 32.
3 Insert the plug into the socket of the pH meter.
4 Connect the original power pack to an easily accessible power
outlet.